Access works did not constitute lawful implementation of a planning permission

Share via email

In the recent case Greyfort Properties v Secretary of State for Communities and Local Government, the Court of Appeal has rejected an attempt by a developer to use a planning permission granted 37 years ago to build 19 flats in Torquay.

Greyfort Properties (G) had submitted an application for a Certificate of Lawful Use or Development that would allow it to carry out the development of 19 flats on the site under a permission granted in 1974, without submitting a fresh planning application.

G had obtained planning permission in 1974 for the development. However, the planning permission included a condition that “before any work is commenced on the site, the ground floor levels of the building hereby permitted shall be agreed with the Local Planning Authority in writing.” The planning permission stipulated that work had to begin within five years. In 1978 – four years from the date of the permission – G carried out some access work, and argued that this work amounted to commencement of the development, meaning that the planning permission remained in force (and therefore a fresh application would not be needed.) However, the planning inspector said that the access works had been carried out in breach of the planning condition, and that the works did not amount to commencement of the development. The planning inspector’s decision was upheld by the High Court.

G appealed this ruling at the Court of Appeal.

The Court of Appeal held that, although preparatory works relating to access for the development were carried out on the site in 1978 within the five-year time limit, these works did not implement the planning permission because the ground levels’ condition had not been satisfied.

The usual rule is that development must commence within three years of the grant of planning permission. Typically, if a developer didn’t want to actively proceed with a development, but wanted to ensure that the planning permission did not expire, they would dig a few holes, maybe lay some foundations and ask the planning officer to write a letter stating that development had commenced.  They could then ‘mothball’ the site until there was a good commercial reason to proceed.

During the recession, I expect some developers have been delaying commencement of developments. This decision reminds us that it is not just a matter of physically commencing development before the end of the three-year period that is important, but that the pre-commencement conditions must also be dealt with before commencement of building works. It can take some months to have the pre-commencement conditions approved, so any developer sitting on a planning permission should not leave it until the last minute to look into this.